The company is currently constructing the 101 KM coal hauling road / overland conveyor which connects the Tabang Project to Muara Pahu barge loading facility. The construction of 101 km is scheduled to finish in Q4 2023. The road will be 14 meters wide, cross 7 rivers including the Belayan River with a bridge of 567 metres, have more than 150 culverts and an all-weather surface which will ultimately be asphalted. This coal hauling road will be aligned with 85 km public road that the company is also currently constructing as part of corporate social responsibility (CSR) projects to improve the access of local communities to ultimately improve their socio-economic welfare.